Company LogoCompany Logo

Pioneering ultra-rapid electric vehicle charging installation for independent forecourt operator

Published: 5 April 2021


We are at the forefront of the £400m investment in ultra-rapid electric vehicle charging points by independent forecourt operator MFG to be installed across 500 of its sites by 2030.

As a strategic electrical consultant partner in the initiative, we advised them technically on the design and development strategy for installation, specifying all of switch gear to be used throughout entire network.

We were on site at the pilot for around six weeks liaising with independent connection providers and network operators, manufacturers of switch gear and suppliers of the EV charging equipment.

We managed the physical installation of cables, earthing arrangements, connection testing, commissioning, emergency stop interface with the fuel system and the supply and installation of all architectural lighting.

The project was delivered on time, on schedule and is a stunning example of the forecourt of future.

Environmental compliance today, creating a sustainable tomorrow

Helping you reduce risk to the environment and your operation by managing assets compliantly while achieving commercial, ESG, and net-zero goals.

Contact our experts